6100 Columbia – Man Door

The project included installation of hollow metal frames, commercial steel doors, and complete hardware packages.

Project Type

Private Industrial Owner

Square Footage

20,000 sq. ft

GC Partner

Columbia

Scope Performed

Precision alignment, proper sequencing, and code-compliant hardware integration

Project Description

This project involved the installation of commercial-grade man doors within an active industrial facility. The scope required precision alignment, proper sequencing, and code-compliant hardware integration to ensure security, durability, and operational efficiency. Field verification and coordination ensured proper swing clearances, fire-rating compliance where required, and smooth integration with existing wall systems.

Execution was completed without disruption to daily facility operations, maintaining schedule integrity and minimizing punch.

Project Timeline

Jan 3, 2022 – Jan 14, 2022

Mobilization & Site Prep

Setting up trailers, tools, materials, safety protocols

Jan 17, 2022 – Feb 11, 2022

Interior Metal Stud Framing

Layout and installation of metal studs for walls and partitions

Feb 14, 2022 – Mar 18, 2022

Drywall Installation & Finishes

Hanging drywall, taping, sanding, and first coat finishes

Mar 21, 2022 – Apr 1, 2022

Acoustical Ceilings

Suspension system installation, tile placement, and final inspections

Apr 4, 2022 – Apr 15, 2022

Door & Hardware Installation

Installation of doors, frames, locks, and hardware

Apr 18, 2022 – May 6, 2022

Architectural Finish Components

Millwork, wall panels, trim, and decorative elements

May 9, 2022 – May 20, 2022

Coordination & Final Punch

Field coordination, inspections, rework corrections, and turnover

May 23, 2022 – May 27, 2022

Project Closeout

Documentation, final inspections, client walkthroughs