7521 Jefferson Ave – Skanska

The interior scope was delivered on schedule with minimal rework. Field coordination ensured smooth inspections and streamlined turnovers.

Project Type

Commercial Construction

Square Footage

25,000 sq. ft

GC Partner

Skanska

Scope Performed

Interior metal stud framing, Drywall and finish systems, Acoustical ceilings

Project Description

Delivered in partnership with Skanska, this project involved comprehensive Division 9 scope execution within an active commercial development. The work required disciplined coordination, structured supervision, and schedule-driven manpower to maintain alignment with overall project milestones.

Our team operated within a multi-trade environment, ensuring framing, drywall, ceilings, and finish elements were installed without disruption to critical path activities.

Project Timeline

Jan 3, 2022 – Jan 14, 2022

Mobilization & Site Prep

Setting up trailers, tools, materials, safety protocols

Jan 17, 2022 – Feb 11, 2022

Interior Metal Stud Framing

Layout and installation of metal studs for walls and partitions

Feb 14, 2022 – Mar 18, 2022

Drywall Installation & Finishes

Hanging drywall, taping, sanding, and first coat finishes

Mar 21, 2022 – Apr 1, 2022

Acoustical Ceilings

Suspension system installation, tile placement, and final inspections

Apr 4, 2022 – Apr 15, 2022

Door & Hardware Installation

Installation of doors, frames, locks, and hardware

Apr 18, 2022 – May 6, 2022

Architectural Finish Components

Millwork, wall panels, trim, and decorative elements

May 9, 2022 – May 20, 2022

Coordination & Final Punch

Field coordination, inspections, rework corrections, and turnover

May 23, 2022 – May 27, 2022

Project Closeout

Documentation, final inspections, client walkthroughs