113 Executive Dr Ste 129

The project included complete interior build-out of office suites, conference rooms, and shared spaces.

Project Type

Private Commercial Developer

Square Footage

10,000 sq. ft

GC Partner

Executive Drive

Scope Performed

Complete interior build-out of office suites, conference rooms, and shared spaces

Project Description

A high-end tenant improvement in a Class-A commercial office building, 113 Executive Drive, Ste 129 was designed to provide a modern, functional workspace for corporate clients. Despite a tight schedule and complex layout, our team executed the interior framing, drywall, acoustical ceilings, doors, hardware, and finish carpentry with precision and minimal disruption to building operations.

The project adhered to the client’s sustainability goals through efficient material use and coordination with building management systems for operational efficiency.

Project Timeline

Jan 3, 2022 – Jan 14, 2022

Mobilization & Site Prep

Setting up trailers, tools, materials, safety protocols

Jan 17, 2022 – Feb 11, 2022

Interior Metal Stud Framing

Layout and installation of metal studs for walls and partitions

Feb 14, 2022 – Mar 18, 2022

Drywall Installation & Finishes

Hanging drywall, taping, sanding, and first coat finishes

Mar 21, 2022 – Apr 1, 2022

Acoustical Ceilings

Suspension system installation, tile placement, and final inspections

Apr 4, 2022 – Apr 15, 2022

Door & Hardware Installation

Installation of doors, frames, locks, and hardware

Apr 18, 2022 – May 6, 2022

Architectural Finish Components

Millwork, wall panels, trim, and decorative elements

May 9, 2022 – May 20, 2022

Coordination & Final Punch

Field coordination, inspections, rework corrections, and turnover

May 23, 2022 – May 27, 2022

Project Closeout

Documentation, final inspections, client walkthroughs