12211 Distribution Way – Demising Walls

This project involved the installation of precise interior demising walls within a large-scale industrial warehouse.

Project Type

Private Industrial Developer

Square Footage

35,000 sq. ft

GC Partner

Distribution Way

Scope Performed

Interior metal stud framing, drywall installation, and finishing for multiple demising partitions.

Project Description

Designed to subdivide open floor space into functional zones, the work required meticulous layout, framing, and finish execution to meet operational and safety requirements.

The project scope included interior metal stud framing, drywall installation, and finishing for multiple demising partitions. Focus was placed on coordination with existing MEP systems and overhead warehouse infrastructure to minimize conflicts and maintain uninterrupted operations.

Project Timeline

Jan 3, 2022 – Jan 14, 2022

Mobilization & Site Prep

Setting up trailers, tools, materials, safety protocols

Jan 17, 2022 – Feb 11, 2022

Interior Metal Stud Framing

Layout and installation of metal studs for walls and partitions

Feb 14, 2022 – Mar 18, 2022

Drywall Installation & Finishes

Hanging drywall, taping, sanding, and first coat finishes

Mar 21, 2022 – Apr 1, 2022

Acoustical Ceilings

Suspension system installation, tile placement, and final inspections

Apr 4, 2022 – Apr 15, 2022

Door & Hardware Installation

Installation of doors, frames, locks, and hardware

Apr 18, 2022 – May 6, 2022

Architectural Finish Components

Millwork, wall panels, trim, and decorative elements

May 9, 2022 – May 20, 2022

Coordination & Final Punch

Field coordination, inspections, rework corrections, and turnover

May 23, 2022 – May 27, 2022

Project Closeout

Documentation, final inspections, client walkthroughs