180 Global Plaza

The project was delivered on schedule with minimal disruption to building operations and a streamlined final turnover process.

Project Type

Confidential Corporate Tenant

Square Footage

30,000 sq. ft

GC Partner

Global Plaza

Scope Performed

Interior metal stud framing, drywall & finish systems, acoustical ceiling installation

Project Description

A full-scale commercial interior build-out within a multi-tenant office tower, 180 Global Plaza required disciplined execution across framing, drywall, ceilings, doors, and architectural finishes. The project demanded tight coordination with base building systems and adjacent trades to maintain schedule integrity and inspection readiness.

Crew scaling aligned with phase transitions to protect critical path. Inspection-ready workflows were implemented at each stage to reduce rework and maintain consistent finish standards.

Project Timeline

Jan 3, 2022 – Jan 14, 2022

Mobilization & Site Prep

Setting up trailers, tools, materials, safety protocols

Jan 17, 2022 – Feb 11, 2022

Interior Metal Stud Framing

Layout and installation of metal studs for walls and partitions

Feb 14, 2022 – Mar 18, 2022

Drywall Installation & Finishes

Hanging drywall, taping, sanding, and first coat finishes

Mar 21, 2022 – Apr 1, 2022

Acoustical Ceilings

Suspension system installation, tile placement, and final inspections

Apr 4, 2022 – Apr 15, 2022

Door & Hardware Installation

Installation of doors, frames, locks, and hardware

Apr 18, 2022 – May 6, 2022

Architectural Finish Components

Millwork, wall panels, trim, and decorative elements

May 9, 2022 – May 20, 2022

Coordination & Final Punch

Field coordination, inspections, rework corrections, and turnover

May 23, 2022 – May 27, 2022

Project Closeout

Documentation, final inspections, client walkthroughs